|
WEST is presenting at the 2007 Offshore Technology Conference.
The
abstract below summarizes the information. If you would like
additional details, please contact us. To obtain a complete copy
of this paper, visit OTC
Papers Online.
OTC-18614-PP
Using BOPs at Pressures in Excess of the Rated Working Pressure
- A Solution for High Pressure Wells?
Description
As a result of a significant redesign of the Expro electro-hydraulic
15K psi Express Seven SSTT (Sub Sea Test Tree) due to customer requirements,
Expro considered the review of an independent third party to be
a useful design step. Accordingly, a risk assessment was contracted
to help ensure the tool was deployed with reliability as high as
reasonably practical. The process included: 1. Component level FMECA
(Failure Modes, Effects, and Criticality Analysis) for hydraulic,
electronic (hardware and software), and mechanical systems, 2. FMECA
of most likely multiple failure situations, and 3. Fault trees of
selected functionality.
Results
and Conclusions
The design operating requirements included not only 15,000 psi,
but also 121ºC maximum temperature. Electronic component selection
included vendor qualification for the required temperatures and
pressures. Wellbore wetted components had the added criteria of
compatibility with completion fluids. In some instances, components
could not be purchased to meet requirements, in which case qualification
procedures were prepared and conducted under the SSTT vendor's direction.
Where adequate standards did not exist for quality and reliability
standards, those from other industries were utilized.
Over
1600 line items were generated to define component failures. These
lines independently analyzed risks for each of four operating modes
in the consequence categories of safety, environmental, and asset
(economic), taking into account consequence severity, exposure,
avoidance/mitigation, and likelihood of occurrence. Those items
with SIL (Safety Integrity Level) 3 or greater were individually
reviewed to determine if additional mitigation was required.
This
paper will review the methodology, assumptions, and recommendations,
as well as revisions that resulted. While the changes recommended
were relatively few considering the depth and breadth of the analysis,
all parties were in agreement that the objectives of design validation
and risk reduction were accomplished.
return
to top
|